Total Working Days

Topic Proposal: 5 days
Literature Review, Precedent Studies, Inventory-Analysis-Synthesis: 11 days
Conceptual Design Process, Preliminary Design: 12 days
Masterplan, Development Area: 15 days
Presentation Board Design, Construction Drawings, Design Report: 26 days

* Total Working Days do not include public holidays, presentation days, weekends, semester breaks

Schedule by Calendar

Please click on the following link for Design Thesis 2007/2008 Calendar:
http://www.localendar.com/public/earthworkstudio